Views 2 is working, although there is still a need for handlers and a user interface to be developed. Also, at the moment, Merlin is working on Panels, but on December 31st, Beta 1 will be released and his focus will shift to Views. On Dec 29, 2007 10:39 AM, Gerhard Killesreiter <gerhard@killesreiter.de> wrote:
-----BEGIN PGP SIGNED MESSAGE----- Hash: SHA1
Hi there,
it is a time honoured tradition that drupal.org is updated to the first release candidate of a new Drupal release as soon as this is available.
The first RC of D6 is now available, now when is that update going to happen?
The answer is unfortunately: Not very soon. The reason is not the release candidate but the multiple dependencies that drupal.org has.
The most well known is probably the project module and it's many friends.
However, there are also other dependencies of which I can't find a D6-ready release or some attempt at one (image.module and simplenews for example).
Project* has it's own roadmap on the D6 update here: http://groups.drupal.org/node/6180
While I am not entirely happy with the order of the items (I'd obviously prefer to have points 10 and 11 at the top), there is at least something to look at. Also, people who would like to see d.o updated do know how they can help. Unfortunately, there aren't that many people who are eager to help.
What I am trying to do is to establish a timeline of when d.o could be updated. So I'd like the maintainers (or other knowledgable parties) to speak up and tell me what their guestimates for updates to D6 are:
- - project - - project_issues - - versioncontrol - - views - - image - - image_gallery - - image_attach - - simplenews - - lists - - feature
Cheers, Gerhard -----BEGIN PGP SIGNATURE----- Version: GnuPG v1.4.6 (GNU/Linux)